SUB-STAGE |
|||||||
|
00 |
20 |
60 |
90 |
||||
|
Registration |
Start of main action |
Completion of main action |
92 |
93 |
98 |
99 |
|
|
00 Preliminary |
00.00 Proposal for new project received |
00.20 Proposal for new project under review |
00.60 Review summary circulated |
00.98 Proposal for new project abandoned |
00.99 Approval to ballot proposal for new project |
||
|
10 Proposal |
10.00 Proposal for new project registered |
10.20 New project ballot initiated |
10.60 Voting summary circulated |
10.92 Proposal returned to submitter for further definition |
10.98 New project rejected |
10.99 New project approved |
|
|
20 Preparatory |
20.00 New project registered in TC/SC work programme |
20.20 Working draft (WD) study initiated |
20.60 Comments summary circulated |
20.98 Project deleted |
20.99 WD approved for registration as CD |
||
|
30 Committee |
30.00 Committee draft (CD) registered |
30.20 CD |
30.60 Comments/ voting summary circulated |
30.92 CD referred back to Working Group |
30.98 Project deleted |
30.99 CD |
|
|
40 Enquiry |
40.00 DIS registered |
40.20 DIS ballot initiated: |
40.60 Voting summary dispatched |
40.92 Full report circulated: DIS referred back to TC or SC |
40.93 Full report circulated: decision for new DIS ballot |
40.98 Project deleted |
40.99 Full report circulated: DIS approved for registration as FDIS |
|
50 Approval |
50.00 FDIS registered for formal approval |
50.20 FDIS ballot initiated: |
50.60 Voting summary dispatched. |
50.92 FDIS referred back to TC or SC |
50.98 Project deleted |
50.99 FDIS approved for publication |
|
|
60 Publication |
60.00 International Standard under publication |
60.60 International Standard published |
|||||
|
90 Review |
90.20 International Standard under periodical review |
90.60 Review summary dispatched |
90.92 International Standard to be revised |
90.93 International Standard confirmed |
90.99 Withdrawal of International Standard proposed by TC or SC |
||
|
95 Withdrawal |
95.20 Withdrawal ballot initiated |
95.60 Voting summary dispatched |
95.92 Decision not to withdraw International Standard |
95.99 Withdrawal of International Standard |
|||
STAGES TO DEVELOP AN INTERNATIONAL STANDARD
|
Project stages |
ISO/IEC Directives Part 1 (1995) |
JTC 1 Procedures (1995) |
New JTC 1 Procedures (1997) |
|
1 Proposal stage |
Acceptance of the New work item proposal NP |
Acceptance of the New work item proposal NP |
Acceptance of the New work item proposal NP |
|
|
Voting during meeting or by correspondence (3 months) |
Voting period: 3 months |
Voting period: 3 months |
|
2 Prepatory stage |
Preparation of the Working Draft WD
|
Preparation of the Working Draft WD |
Preparation of the Working Draft WD |
|
3 Committee Draft stage |
Production and acceptance of the Committee Draft CD
|
Production and acceptance of the Committee Draft CD |
Production and acceptance of the Committee Draft CD |
|
|
Voting period: 3 to 6 months
|
Voting period: 3 to 6 months |
Voting period: 3 to 6 months |
|
4 Enquiry stage |
Production and acceptance of the Draft International Standard DIS |
|
Acceptance of the Final Committee Draft FCD |
|
|
Voting period: 5 months
|
Production and approval of the |
Voting period: 4 to 6 months |
|
5 Approval stage |
Approval of the Final Draft International Standard FDIS
|
Draft International Standard DIS
|
Approval of the Final Draft International Standard FDIS |
|
|
Voting period: 2 months
|
Voting period: 4 months |
Voting (Yes/No): 2 months |
|
6 Publication stage |
Publication of the International Standard ISO or ISO/IEC
|
Publication of the International Standard ISO/IEC |
Publication of the International Standard ISO/IEC |